Launch Slideshow

Image

The challenge of a lifetime

The challenge of a lifetime

  • Image

    http://www.pwmag.com/Images/tmpDDF%2Etmp_tcm111-1349850.jpg?width=300

    true

    Image

    300

    “It can be done,” says Dave Zanetell, manager of the Hoover Dam Bypass project for the Central Federal Lands Highway Division of the Federal Highway Administration. “It doesn't have to be that every great endeavor becomes a legacy that's hard to manage fiscally.” Photos: Federal Highway Administration, Central Federal Lands Highway Division

  • Image

    http://www.pwmag.com/Images/tmpDE0%2Etmp_tcm111-1349851.jpg?width=300

    true

    Image

    300

    The terrain on the Nevada rim varies, with rock outcroppings and fault lines traversing the canyon walls.

  • Image

    http://www.pwmag.com/Images/tmpDE1%2Etmp_tcm111-1349852.jpg?width=300

    true

    Image

    300

    With Hoover Dam defining the special character of the site, focus groups decided on a deck arch to preserve the view of the historic dam.

  • Image

    http://www.pwmag.com/Images/tmpDE3%2Etmp_tcm111-1349854.jpg?width=300

    true

    Image

    300

    Twin ribs were designed to lessen the size of arch elements during construction and provide greater flexibility for geometry control as the arch was cast.

  • Image

    http://www.pwmag.com/Images/tmpDE2%2Etmp_tcm111-1349853.jpg?width=300

    true

    Image

    300

    Two highline cable cranes that delivered and placed material were supported by two 330-foot towers, each 2,500 feet apart. A trolley was placed on the cable system. The towers were designed to move left or right seven degrees to allow workers to remove steel girders.


CONCRETE IN 100° F

In early 2005 the Obayashi/PSM JV construction team began assembling onsite. One of the chief topics of discussion was how 5,000 workers built the 726-foot Hoover Dam in temperatures that can exceed 130° F. The team also faced the same logistical puzzle their general contractor counterpart on the Hoover Dam — Six Companies Inc. — had solved back in 1931: transporting crews, equipment, and materials to the site.

But a single challenge dwarfed all others: the concrete arches. Building them required a new approach to mix design, thermal control, concrete delivery and placement, consolidation, and quality control.

Work began two years before the first arch segment was cast. The design and ownership team required 10,000 psi in 56 days, aggregate selection for durability, and thermal control requirements to minimize cracking. The construction team added several more requirements to overcome delivery and placement challenges: pumpability, or the ability to physically push the concrete through 600 feet of slickline up 275 feet; flowability issues that allow for enough slump to flow freely into forms (between 7- to 8-inch slump); and the long set time (at least three hours before the concrete began setting in case of mechanical breakdowns, placement issues, and batching or pumping problems).

To those design requirements the construction team added several others to overcome delivery and placement challenges (pumpability, flowability, and long set time) as well as schedule challenges (rapid strength gain to keep the form traveler cycle time minimal).

Strength targets were addressed by a high cementitious material content (800 pounds of cement and 200 pounds of fly ash per cubic yard) and a very low water-to-cement ratio (less than 0.31), which typically achieved strengths of 4,000 psi in a little more than a day and more than 12,000 psi in 56 days.

Pumpability and flowability were addressed by use of the Sika 2100 water-reducing superplasticizer, which resulted in concrete slump ranges that neared those of self-consolidating concrete. Long set times in excess of 2.5 hours were achieved using a Sika MP retarder.

However, the rich mix design made it difficult to work in such high temperatures.

The concrete in its natural curing condition would reach temperatures in excess of 190° F, far above the 155° limit of the contract specifications. Most typical mitigation methods (using chilled batch water or ice chips, shading the aggregate stockpiles, and pouring at night) would not reduce the maximum curing temperature to within the target range.

Only two realistic options remained: circulation of cold water through pipes embedded in the concrete or the use of liquid nitrogen to precool the concrete to a temperature such that its maximum peak curing temperature would be less than 155° F. Miles of cooling tubes had been used to control curing temperatures during construction of Hoover Dam, but the location, cycle time, installation, and maintenance issues involved ruled out their use.

This made liquid nitrogen the only option, allowing the team to drop the batched temperature of 85° F to a pre-delivery temperature of 40°. That maintained the temperature at point of placement in the 60° F range, resulting in peak curing temperatures of less than 150°.

Given the heat of a Southern Nevada summer, liquid nitrogen costs often exceeded $100/cubic yard. But the process eliminates other costs, such as maintaining a consistent water supply, grouting cooling tubes, or leaving forms in place for an extended duration. During the hottest times the team filled the concrete pumping slick line with chilled water before the pour and wrapped it with burlap soaked in chilled water to reduce heat gain through the placement system.

“Every aspect of each construction contract and the approach to risk management and contract execution was simply a natural extension of the development effort,” says Dave Zanetell, manager of the Hoover Dam Bypass project for the Central Federal Lands Highway Division (CFLHD) of the Federal Highway Administration (FHWA). “The goal simply never was to ‘create a design' or to ‘award a contract.' It was to ‘complete the project' by integrating the world's best design capabilities with those of the world's best construction contractors.”

“The main outcome we want to create is a sense of possibility,” Zanetell explains. “Great things can and should be done. It doesn't have to be that great civil works also leave an uncertain fiscal legacy. We can do both — achieve greatness and do it as planned.

It's the optimism of a man who has supervised the massive undertaking for nearly a decade, an undertaking that has brought together dozens of public agencies, consultants, and contractors who have employed 1,200 tradesmen and 300 engineers.

What's more is that the project will be completed both on budget and on quality without dispute or claim — a major success of the project management team.

“It's about setting in place clear, defined roles of technical coordination and bringing design, construction, and technical expertise together,” Zanetell adds. “We've created synergies instead of stove-pipes, allowing world experts to bring their vast knowledge yet aligning under a common framework,” noting that a project of this magnitude mandates engagement from the industry's best.

CFLHD managed all aspects of the decision process and integration so that no firm or entity could supersede another. “It was a departure from the all-too-frequent model in which the owner ultimately becomes captive to the decisions of others then is left only to resolve the inevitable disputes and claims,” he says.

The successful project management is the result of FHWA's cradle-to-grave delivery approach in which designers, engineers, and builders have remained part of the process even after their individual tasks have been completed, coming together through specifically structured points of interface and engagement throughout the project's execution. “Major jobs have big turnover. With something of this duration there's always a lot of change over the course of people's careers. They start the project and then move on, but our stakeholders have remained committed to the project.”

Each project management document — the delivery plan, detailed multiagency operating agreement for roles and responsibilities, and programmatic agreement for architectural and historic guidance — was explicitly endorsed by all stakeholders to ensure CFLHD could commission and manage consultant deliverables without risk of costly delay or redirection. The documents also served to further the understanding of the roles to allow the leads from each team to work seamlessly on overlapping and parallel segments of the project.

Zanetell notes that one unique aspect of the plan was to also establish and define an executive committee made up of the heads of each agency, who then served to provide guidance and endorsement of the most sensitive and scope-defining aspects of the project.

For Zanetell, the bypass project furthers the potential for the future of great civil works projects just as the nearby Hoover Dam project did nearly 75 years ago. “It has been a team effort, everyone in every way making this project a reality.”

— Goodyear (david.goodyear@tylin.com) is senior vice president of T.Y. Lin International and the design engineer of record on the bypass project; St. John (jeffsj@obayashi-usa.com) is the project manager of Obayashi/PSM JV and the contractors' project manager for the bypass project.

Web Extra

Do you receive our PUBLIC WORKS Updates? If not, sign up for the free e-newsletter here. We'll include an exclusive, online-only look into the challenges faced on the Hoover Dam Bypass in our Sept. 1 edition. You can also find the content here.